【摘要】 柱箍筋配置量的定量计算一直是工程设计人员关心的问题 ,PUSHOVER方法为柱箍筋的配置定量计算的实现提供了可能。从三个方面探讨了柱箍筋的计算 ,指出了抗震设计规范构造配箍在高地震烈度下的不足
【Abstract】 The calculation of the stirrups quantity of columns is one of the most concerned things to the structure designers,the PUSHOVER makes it possible to realize the calculation of the strirrups quanitity of columns,the calculation method of the stirrups quantity in three aspects is discussed,it is pointed out that the stirrups quantity of columns is sometimes insufficient with the current aseismic design code under major earthquakes.
【关键词】 预应力混凝土;
框架柱;
箍筋;
【Key words】 prestressed concrete\ columns of frame structures\ stirrups quantity;
【Key words】 prestressed concrete\ columns of frame structures\ stirrups quantity;
- 【文献出处】 工业建筑 ,Industrial Construction , 编辑部邮箱 ,2002年10期
- 【分类号】TU378.4
- 【被引频次】4