外海超长沉管隧道设计关键技术研究
Research on Key Design Technology of Extra-long Immersed Tunnel in Open Sea
【摘要】 以港珠澳大桥沉管隧道工程为依托,分析了外海超长沉管隧道设计需要解决的关键技术,重点介绍了沉管隧道基础沉降控制技术、多点非一致地震激励下超长沉管隧道设计方法、节段接头构造形式研究及高水压120年设计使用寿命OMEGA止水带研发等需要突破的技术,并阐述了主要研究成果。这些研究成果为我国后续外海超长沉管隧道设计提供技术支撑。
【Abstract】 Based on the immersed tunnel project of Hong Kong-Zhuhai-Macao Bridge,four key design technologies of open sea extra-long immersed tunnel are analyzed:foundation settlement control technology of immersed tunnel(IMT),seismic design method of extra-long IMT subjected to non uniform seismic excitations,structure type of IMT segmental joint,and development of OMEGA seal with the designed service life of 120 years.The main research results are summarized which will provide technical supports for the construction of IMT projects in future.
【关键词】 沉管隧道;
设计关键技术;
基础沉降控制;
非一致地震激励;
节段接头构造;
研究;
【Key words】 immersed tunnel; key design technology; foundation settlement control; non-uniform seismic excitation; structure type of segmental joint; study;
【Key words】 immersed tunnel; key design technology; foundation settlement control; non-uniform seismic excitation; structure type of segmental joint; study;
【基金】 国家科技支撑计划课题,项目编号2011BAG07B01
- 【文献出处】 公路 ,Highway , 编辑部邮箱 ,2015年04期
- 【分类号】U452.2
- 【被引频次】2
- 【下载频次】166