节点文献

地铁重叠隧道施工顺序研究

Study on the construction sequence of overlapped metro tunnels

  • 推荐 CAJ下载
  • PDF下载
  • 不支持迅雷等下载工具,请取消加速工具后下载。

【作者】 林刚

【Author】 Lin Gang(The Second Survey & Design Institute,C.R.E.C., Chengdu 610031)

【机构】 铁道第二勘察设计院 成都610031

【摘要】 文章以深圳地铁三号线老-东区间盾构隧道工程为背景,采用有限元数值模拟研究方法,对地铁重叠隧道段在地表无任何建筑物和地表有房屋基础两种工程条件下,采用先上洞后下洞和先下洞后上洞两种施工顺序的盾构区间隧道施工全过程的力学行为进行了分析对比。通过分析,揭示出了相关的研究成果与实际施工顺序不同的关键所在,可为今后类似工程的设计与施工提供参考。

【Abstract】 In accordance with the shield tunneling of the transit tunnels on line 3 of Shenzen metro,a comparative study was carried out by finite element numerical simulation on the behavior of the whole construction process of the overlapped tunnels,considering two cases: with building foundations or without buildings on ground surface on the overlap section and two options of construction sequence: upper tunnel excavated first and lower tunnel second or lower tunnel excavated first and upper tunnel second.The study revaeled the key points for the contradictions between the relevant research results and the actual construction process.The study can be taken for reference by similar design and construction.

  • 【文献出处】 现代隧道技术 ,Modern Tunnelling Technology , 编辑部邮箱 ,2006年06期
  • 【分类号】U455.4
  • 【被引频次】28
  • 【下载频次】298
节点文献中: 

本文链接的文献网络图示:

本文的引文网络