节点文献

隧道施工废水处理研究

Study on Wastewater Treatment During Tunnel Construction

  • 推荐 CAJ下载
  • PDF下载
  • 不支持迅雷等下载工具,请取消加速工具后下载。

【作者】 周文哲

【Author】 ZHOU Wenzhe;China Railway First Survey and Design Institute Group Co.Ltd.;

【机构】 中铁第一勘察设计院集团有限公司

【摘要】 首先介绍了隧道施工废水的来源、水质特点以及国内外隧道施工废水的处理情况,然后对郑万线小三峡隧道施工废水进行了现场试验。结果表明:现有隧道施工废水中污染物以高浓度悬浮物(SS)为主,还含有少量的化学需氧量、氨氮、石油类等;混凝沉淀对SS去除率为86.0%~89.4%,气浮对SS的去除率为7.1%~21.3%,过滤对SS的去除率为52.9%~64.7%。气浮对SS的去除效果不佳。因此当废水中石油类污染物含量很低,满足污水综合排放标准时,建议取消气浮环节。

【Abstract】 Firstly,the source of tunnel construction wastewater,the characteristics of water quality and the treatment of tunnel construction wastewater at home and abroad were introduced,and then the field tests were carried out on the wastewater from Xiaosanxia Tunnel construction in Zhengzhou-Wanzhou railway. The results show that the pollutants in the existing tunnel construction wastewater mainly contains high concentration suspended solids(SS)and also contains a small amount of chemical oxygen demand,ammonia nitrogen,petroleum and so on,the removal rate of SS by coagulation and sedimentation is 86.0% ~ 89.4%,the removal rate of SS by air floatation is 7.1% ~ 21.3% and the removal rate of SS by filtration is 52.9% ~ 64.7%. It is concluded that the removal effect of air floatation on SS is not good. Therefore,when the content of petroleum pollutants in wastewater is very low and meets the discharge standard of wastewater,it is recommended to remove the air floatation process.

【基金】 中国铁路总公司科技研究开发计划(2016G002-P)
  • 【文献出处】 铁道建筑 ,Railway Engineering , 编辑部邮箱 ,2019年09期
  • 【分类号】U455;X731
  • 【被引频次】7
  • 【下载频次】157
节点文献中: 

本文链接的文献网络图示:

本文的引文网络