新疆叶尔羌河中游渠首工程地基处理设计
The Design of Foundation Treatment of Canal Head-works at Middle Reaches of Yarkant River in Xinjiang
【摘要】 叶尔羌河洪水动态规律极为复杂,以其极高的起涨速率、异常的高洪峰值闻名于世。中游渠首地基是粘粒极少、极松散的粉细沙层。针对其特点,采用振冲挤密砂石桩、防渗防冲连续墙、抗冲柔性土工布金属网格石笼等综合处理措施进行设计。
【Abstract】 The Yarkant River flood dynamic rule is extremely complex,extremely high rises the speed by it,the unusual high flood peak value is world famous.Middle reaches canal head foundation is the non-cohesive soil,extremely loose silt sand.In view of its characteristic,uses inspires crushing sand,Erosion control seepage control Continuous wall,ero-sion-resisting flexibility geotechnical engineering Ge-bin-shi-long and so on synthesis processing measures to carry on the design.
【关键词】 粉细沙地基;
地震液化;
防渗防冲;
承载力;
设计;
【Key words】 silt sand foundation; the earthquake deliquesces; erosion control and seepage control; bearing capacity; design Abstrac: The Yarkant River flood dynamic rule is extremely complex,extremely high rises the speed by it,the unusual high flood peak value is world famous.Middle reaches canal head foundation is the non-cohesive soil,extremely loose silt sand.In view of its characteristic,uses inspires crushing sand,Erosion control seepage control Continuous wall,erosion-resisting flexibility geotechnical engineering Ge-bin-shi-long and so on synthesis processing measures to carry on the design.;
【Key words】 silt sand foundation; the earthquake deliquesces; erosion control and seepage control; bearing capacity; design Abstrac: The Yarkant River flood dynamic rule is extremely complex,extremely high rises the speed by it,the unusual high flood peak value is world famous.Middle reaches canal head foundation is the non-cohesive soil,extremely loose silt sand.In view of its characteristic,uses inspires crushing sand,Erosion control seepage control Continuous wall,erosion-resisting flexibility geotechnical engineering Ge-bin-shi-long and so on synthesis processing measures to carry on the design.;
- 【文献出处】 水力发电 ,Water Power , 编辑部邮箱 ,2007年05期
- 【分类号】TV223
- 【下载频次】95