节点文献
三塘湖风电场二、三、四期风机基础优化设计
Optimized design of wind turbine foundation of Santanghu Wind Farm project phases Ⅱ and Ⅲ and Ⅳ
【摘要】 以新疆哈密三塘湖风电场为例,介绍了整个工程的基本情况,分析了二、三、四期风机基础的优化过程。优化后节约了混凝土用量,节省了工程投资。
【Abstract】 Taking Santanghu Wing Farm in Hami Xinjiang as example,the general information of the whole project was introduced. The optimization process of the wind turbine foundation design for project phase Ⅱ,phase Ⅲ and phase Ⅳ was analyzed. The used amount of the concrete was decreased due to the optimization,and the project investment was reduced.
【关键词】 风机基础;
地震力;
运行荷载;
优化设计;
【Key words】 wind turbine foundation; earthquake force; operational load; optimized design;
【Key words】 wind turbine foundation; earthquake force; operational load; optimized design;
- 【文献出处】 华电技术 ,Huadian Technology , 编辑部邮箱 ,2013年09期
- 【分类号】TM614
- 【下载频次】49