下游折坡点位置对重力坝抗震性能的影响

Influence of downstream turning point on seismic performance of gravity dam

  • 推荐 CAJ下载
  • PDF下载
  • 不支持迅雷等下载工具,请取消加速工具后下载。

【作者】 曹学兴何蕴龙冯蕊熊堃

【Author】 CAO Xuexing;HE Yunlong;FENG Rui;XIONG Kun;State Key Laboratory of Water Resources and Hydropower Engineering Science,Wuhan University;Huaneng Lancang River Hydropower Co. ,Ltd.;Changjiang Institute of Survey,Planning,Design and Research;National Dam Safety Research Center;

【机构】 武汉大学水资源与水电工程科学国家重点实验室华能澜沧江水电有限公司长江勘测规划设计研究院国家大坝安全工程技术研究中心

【摘要】 为分析重力坝下游折坡点位置对其抗震性能的影响,从震害工程及有限元计算两方面分析重力坝的抗震性能。结果表明:下游折坡点位置过低将对重力坝抗震性能带来不利影响;坝颈部位应力随下游折坡点位置的降低而增大,且增幅随坝高的增加而增大。为保证大坝具有良好的抗震性能,工程设计中下游折坡点位置不宜取太低,在8度及以上地震烈度区,100 m高重力坝折坡点位置不宜低于坝高的20%。云南某水电站水库计算结果表明:大坝在设计地震作用下,坝颈部位产生了明显的应力集中,并出现裂缝;当地震超载系数为1.17时,坝颈部位上下游的裂缝贯通,大坝抗震性能较差,在工程设计中应合理提高下游折坡点的位置。

【Abstract】 The influence of the downstream turning point on the seismic performance of a gravity dam was studied through earthquake projects and finite element calculation.The results show that a position of the downstream turning point that was too low had adverse effects on the seismic performance of the gravity dam.The stress of the neck of the dam increased with the descending position of the downstream turning point and the ascending height of the dam.To ensure good seismic performance of the dam,the position of the downstream turning point should not be too low in project design;it should not be lower than 20% of the height of the dam for a 100 m-high gravity dam in areas with an earthquake intensity of eight or an even higher degree.Linear elastic and nonlinear dynamic finite element analysis were conducted for a practical project in a hydropower station in Yunnan Province.The calculation results show that,under the design earthquake effects,obvious stress concentration and cracks appeared in the neck of the dam.When the earthquake overload coefficient was 1.17,the upstream cracks joined the downstream cracks in the neck of the dam,indicating that the seismic performance of the dam was very poor.The downstream turning point should be reasonably improved in project design.

【基金】 国家大坝安全工程技术研究中心研发课题(2011NDS021);中国博士后科学基金(2012M511594);国家大坝安全工程技术研究中心开放基金(NDSKFJJ1103)
  • 【文献出处】 河海大学学报(自然科学版) ,Journal of Hohai University(Natural Sciences) , 编辑部邮箱 ,2013年05期
  • 【分类号】TV642.3;TV312
  • 【被引频次】1
  • 【下载频次】62