三峡厂房坝段三维静动力分析

Static and Dynamic Analysis for Power House Section of Three Gorges Dam

  • 推荐 CAJ下载
  • PDF下载
  • 不支持迅雷等下载工具,请取消加速工具后下载。

【作者】 吴旭光马贞信

【Author】 Wu Xuguang Computer Center,Hohai Univ.Ma Zhenxing Dept.of Architectural Engineering,Hohai Unive.

【机构】 河海大学计算中心河海大学建筑工程系

【摘要】 本文对三峡厂房河床坝段进行三维静、动力有限元分析,着重分析发电孔洞、坝踵、坝趾以及发电管道上下弯道处的应力分布。研究表明,当水库满载运行时,坝踵处产生较大局部拉应力;管道进出口也出现较大局部拉应力。在地震作用下,发电管道进出口和坝踵处由于刚度突变,动力反应相当明显,动应力较大。

【Abstract】 The 3-D static and dynamic finite element analysis is conducted for the powerhouse section of the dam of the Three Gorges Project,especially for the stress state at the dam heel,the toe dam, the poper generation outlet and the poper penstock.Research indicates that under full load operation of the reservoir,large local tensile stress will be produced at the dam heel and the outlet and inlet of the power penstock.Under the action of earthquakes,because of the abrupt change of stiffness at the dam heel and the outlet and inlet of the power penstock,the dynamic response is very obvious and the dy- namic stress is large.

  • 【分类号】TB122
  • 【下载频次】36
节点文献中: 

本文链接的文献网络图示:

本文的引文网络