节点文献

地震作用下软母线连接的变电站设备建模与分析

Modeling and Analysis of Substation Equipment Interconnected by Flexible Bus under Seismic Action

  • 推荐 CAJ下载
  • PDF下载
  • 不支持迅雷等下载工具,请取消加速工具后下载。

【作者】 陈辉王健生谢强

【Author】 CHEN Hui;WANG Jiansheng;XIE Qiang;Department of Building Engineering,Tongji University;Henan Electric Power Survey & Design Institute;

【机构】 同济大学建筑工程系河南省电力勘测设计院

【摘要】 由于软母线的牵拉作用,强地震作用下软母线连接的变电站设备将产生强烈的相互作用。将变电站设备简化为具有一定抗侧移刚度的单自由度体系,软母线简化为变刚度的弹簧,并根据悬索理论求得变刚度弹簧的等效刚度,建立了软母线连接电气设备耦联体系单跨结构的动力学模型,采用Newmark-β法结合牛顿迭代对其进行数值求解。通过对其结构特征以及设备参数的分析发现:软母线中张力刚度随水平跨度呈非线性增长,耦联体系的特征频率受单体设备的自振频率、质量比值及软母线等效刚度的影响。在地震作用下,存在一个关键垂跨比,当软母线的垂跨比小于此关键垂跨比时,母线中产生的水平拉力较大,且设备的地震响应受设备的频率比影响较大。在进行软母线连接的变电站设备的抗震设计时,必须考虑关键垂跨比的影响。

【Abstract】 Because of the pull effect of flexible bus,strong interaction exists in substation equipment interconnected by flexible bus during severe earthquake. The substation equipment was simplified as a single degree of freedom system with lateral stiffness,and the flexible bus was simplified as a spring with variable stiffness. The effective stiffness of the spring was obtained according to the suspension theory. Then a kinetic model of single span structure was built for the electrical coupling equipment interconnected by flexible bus,and solved by using the Newmark-β method combined with Newton iteration. Through the analysis of the structural features and equipment parameters,it shows that the tension stiffness of flexible bus has a nonlinear growth with horizontal span,and the characteristic frequency of coupling system is influenced by the natural frequency of standalong equipment,the quality ratio and the effective stiffness of flexible bus. It is found that there is a critical rise-span ratio under seismic action. When the rise-span ratio of flexible bus is smaller than the critical ratio,large tension generates in the bus,and the seismic response of equipment is greatly influenced by equipment frequency. So during the seismic design of substation equipment interconnected by flexible bus,the influence of critical risespan ratio must be considered.

【基金】 科技部国家重点实验室基金项目(SLDRCE 10-B-01);国家电网公司科技项目(2008-508)
  • 【文献出处】 电力建设 ,Electric Power Construction , 编辑部邮箱 ,2013年10期
  • 【分类号】TM63;TM743
  • 【网络出版时间】2013-10-16 21:33
  • 【被引频次】2
  • 【下载频次】80