滨海核电厂厂坪标高优化

Optimal Design of Floor Elevation for Coastal Nuclear Power Plant

  • 推荐 CAJ下载
  • PDF下载
  • 不支持迅雷等下载工具,请取消加速工具后下载。

【作者】 江才俊佘靖策侯平利

【Author】 JIANG Cai-jun,SHE Jing-ce,HOU Ping-li(China Nuclear Power Design Company Ltd.(Shenzhen),Shenzhen 518057,Guangdong Province,China)

【机构】 深圳中广核工程设计有限公司

【摘要】 确定滨海核电厂厂坪标高主要考虑的因素有厂址设计基准洪水位、循环水泵运行费用和场地土石方挖填平衡。在满足厂址设计基准洪水位要求的情况下,厂坪标高的确定与常规岛侧主厂房布置方案密切相关。对常规岛侧主厂房局部下沉、整体下沉等4种不同布置方案进行了技术经济性分析,得到了最优的厂坪标高。

【Abstract】 The main factors to be considered in determining the floor elevation of coastal nuclear power plant include the site design datum flood level,the operation cost of circulating pumps and the balance of earth-rock.When the requirement of site design datum flood level is satisfied,determination of the floor elevation is closely related to the layout of the main power plant on the conventional island side.In this paper,through a case study of a coastal nuclear power plant under construction,a technical and economic comparison is carried out on the 4 different layout schemes of main power plant on the conventional island side and the optimal plant floor elevation is obtained.

  • 【文献出处】 电力建设 ,Electric Power Construction , 编辑部邮箱 ,2010年08期
  • 【分类号】P731.23;TM623.1
  • 【被引频次】3
  • 【下载频次】45